DATE: July 20, 2024 (Saturday)

TIME:

A. 06:00AM – 08:15AM & 06:00PM – 07:00PM

B. 06:00AM – 04:00PM & 06:00PM – 07:00PM

C. 06:00AM – 07:00PM

PURPOSE:

A.1. NGCP to conduct the opening of 3-Way ABS at STR#215 of Nagsaag – Tumana 69kV Line Segment facing Libertad, Tayug;

2. NGCP to conduct the isolation of tapping point of PANELCO III Tayug II SS at STR#195 of Tumana – Libertad 69kV Line Segment & Correction of TL Defects;

3. NGCP to conduct the closing of 3-Way ABS at STR#215 of Nagsaag – Tumana 69kV Line Segment facing Libertad, Tayug;

4. NGCP to conduct the reconnection of tapping point of PANELCO III Tayug II SS at STR#195 of Tumana – Libertad Line Segment;

B.1. Relocation of pole due to building and driveway construction along Tayug – Natividad Road, Brgy. A, Tayug (Double Circuit Line);

2. Correction of Three Phase Circuit Line Technical Punchlist;

3. Right of Way Clearing Activity;

C.1. To facilitate the installation, testing and commissioning of the newly acquired SF6 Circuit breaker of the Barangobong 10MVA SS;

2. Correction of Three Phase Circuit Line Technical Punchlist

AFFECTED AREAS:

A. TAYUG – Entire Municipality;

B. NATIVIDAD – Entire Municipality;

TAYUG – Brgys. Trenchera, Carriedo, Poblacion A (Quezon Blvd.), Poblacion B (Bonifacio St., Burgos St., Plaridel St.), Poblacion C (Zamora St.);

C. STA. MARIA – Entire Municipality;

SAN NICOLAS – Entire Municipality;

TAYUG – Brgys. Agno, Amistad, Barangobong, C. Lichauco, Evangelista, Lawak, Legaspi, Old and New Magallanes, Poblacion B (Antiporda St.), Pugot, Saleng, Sto. Domingo, Zamora

All works maybe finished ahead of time and power maybe restored earlier than or as scheduled, so please consider all lines and equipment energized at all times.

SOURCE: PANELCO III Facebook Page